A Study of the Factors Affecting Real-Time Completion of Construction Projects in Al-Haraba City, Libya
DOI:
https://doi.org/10.65405/d4hb6s44Keywords:
Construction delays; Project completion; Relative Importance Index (RII); Stakeholder perspectives; LibyaAbstract
Timely completion of construction projects remains a critical challenge in developing and post-conflict environments such as Libya, where persistent delays negatively affect project performance and economic development. This study investigates the factors affecting the real-time completion of construction projects in Al-Haraba city, Libya, based on stakeholder perceptions. A structured questionnaire survey was administered to construction professionals (n = 68), and the Relative Im-portance Index (RII) method was used to rank delay factors at both individual and group levels. The findings indicate that scheduling and control issues ranked highest (average RII = 0.7735), followed by financial constraints and change-related conditions, while stakeholder-specific differences were also observed. The results provide context-relevant evidence to support practical delay mitigation strategies and improve project delivery in the Libyan construction sector.
Downloads
References
Abubaker, A. Early-stage planning and scheduling accuracy in project delivery. Proc. Inst. Civ. Eng.
2008, 161, 1–10.
Aibinu, A.A.; Jagboro, G.O. The effects of construction delays on project delivery in Nigeria. Int. J. Proj. Manag. 2002, 20, 593–599.
Alfakhri, A.; Rashid, K.; Kaka, A. Causes of delay in Libyan construction projects: Stakeholder per-spectives. Int. J. Constr. Manag. 2017, 17, 1–12.
Alfakhri, A.; Rashid, K.; Kaka, A. Impacts of delays on construction stakeholders in Libya. Built Environ. Proj. Asset Manag. 2018, 8, 1–15.
Assaf, S.A.; Al-Hejji, S. Causes of delay in large construction projects in Saudi Arabia. Int. J. Proj. Manag. 2006, 24, 349–357.
Aziz, R.F. Ranking of delay factors in construction projects (evidence from developing context). Alexan-dria Eng. J. 2013, 52, 387–406.
Creswell, J.W.; Creswell, J.D. Research Design: Qualitative, Quantitative, and Mixed Methods Ap-proaches, 5th ed.; SAGE: Thousand Oaks, CA, USA, 2018.
Pich, M.T.; Loch, C.H.; De Meyer, A. On uncertainty, ambiguity, and complexity in project management.
Manag. Sci. 2002, 48, 1008–1023.
Doloi, H.; Sawhney, A.; Iyer, K.C.; Rentala, S. Analysing factors affecting delays in Indian construction projects. Int. J. Proj. Manag. 2012, 30, 479–489.
Field, A. Discovering Statistics Using IBM SPSS Statistics, 4th ed.; SAGE: London, UK, 2013.
González, P.; González, V.; Molenaar, K.; Orozco, F. Analysis of causes of delay and time overrun in construction projects. J. Constr. Eng. Manag. 2014, 140, 04013027.
Haseeb, M.; Xinhai-Lu; Bibi, A.; Dyian, M. Problems of projects and effects of delays in the construction industry of Pakistan. Aust. J. Bus. Manag. Res. 2011, 1, 41–50.
Hraisha, M.; Al Jorf, S. Developing a knowledge base for construction delay mitigation. J. Constr. Dev. Ctries. 2015, 20, 1–18.
Joshi, A.; Kale, S.; Chandel, S.; Pal, D.K. Likert scale: Explored and explained. Br. J. Appl. Sci. Technol. 2015, 7, 396–403.
Mahamid, I. Schedule delay in construction projects: Review and contextual evidence. J. Eng. Proj. Prod. Manag. 2017, 7, 1–12.
Odeh, A.M.; Battaineh, H.T. Causes of construction delay: Traditional contracts. Int. J. Proj. Manag.
2002, 20, 67–73.
Salam, H.A.A. The most important causes of delays in highway construction projects (Libya). Sabha University Scientific Journal 2020.
Sambasivan, M.; Soon, Y.W. Causes and effects of delays in Malaysian construction industry. Int. J. Proj. Manag. 2007, 25, 517–526.
Shebob, A.; Dawood, N.; Xu, Q. Analyzing construction delay factors: A case study of a building construction project in Libya. In Proceedings of the 27th Annual ARCOM Conference; Bristol, UK, 5–7 September 2011; pp. 1005–1012.
Tavakol, M.; Dennick, R. Making sense of Cronbach’s alpha. Int. J. Med. Educ. 2011, 2, 53–55. Trauner, T.J.; Manginelli, W.A.; Lowe, J.S.; Nagata, M.F.; Furniss, B.J. Construction Delays: Under-
standing Them Clearly, Analyzing Them Correctly; Butterworth-Heinemann: Burlington, MA, USA,
2009.
Tumi, S.A.H.; Omran, A.; Pakir, A.H.K. Causes of delay in construction industry in Libya. The Int. Conf. on Econ. and Admin. Sci. 2009, 265–272.
Ward, S.; Chapman, C. Stakeholders and uncertainty in projects (implications for delay risk). Int. J. Proj. Manag. 2008, 26, 1–10.
Zidane, Y.J.T.; Andersen, B. The top 10 universal delay factors in construction projects. Int. J. Manag. Proj. Bus. 2018, 11, 650–672.
Downloads
Published
Issue
Section
License
Copyright (c) 2025 Comprehensive Journal of Science

This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.